Delivery Order EPR51110-0031

Award Date 10/6/16
Potential Completion Date 5/31/18
Potential Value $2.6M
Federal Agency
EPA Region 5
Ultimate Awardee
Not listed
Federal Contract Vehicle
Set-Aside Type
No Set-Aside Used
Extent Competed
Full and Open Competition after exclusion of sources
Major Defense Program
Not listed
Pricing Type
Firm Fixed Price
Place of Performance
Duluth, MN 55807, USA
Solicitation Procedures
Architect-Engineer FAR 6.102
Number Of Offers Received
Not listed
Legislative Mandate
Not listed
National Interest Action
Not listed
Research Type
Not listed
Primary Consortia Member
Not listed
Similar Awards
This federal contract award to EA Engineering, Science, and Technology, Inc., PBC is for a new task order under an existing contract (EP-R5-11-10) to conduct pre-design investigations for the GLLA SPIRIT LAKE remediation project. The $179,681 firm-fixed-price delivery order was awarded by the Environmental Protection Agency (EPA) Region 5 and is a follow-on to a previous feasibility study completed by EA Engineering under the same contract. The contract involves data collection and other...
The Environmental Protection Agency (EPA) Region 5 awarded a $5,202,621.68 firm fixed price delivery order contract to EA Engineering, Science, and Technology, Inc., PBC (EA Engineering) for the GLLA Spirit Lake Remedial Design Project. The contract will provide a remedial design package, including an engineer's cost estimate, plans, specifications, and habitat restoration design to implement the remediation project. Key subcontractors include Southeastern Archaeological Research, Inc. (a...
This is a $13,811,811.08 firm fixed-price delivery order contract awarded by the U.S. Environmental Protection Agency (EPA) Region 5 to EA Engineering, Science, and Technology, Inc., PBC, a for-profit environmental consulting and engineering firm. The contract is for the SPIRIT LAKE REMEDIAL ACTION - PHASE 3 project, which is part of the EPA's Great Lakes National Program Office (GLNPO) remediation and restoration efforts. This is a non-set-aside contract. The prime contractor, EA Engineering,...
This is a delivery order contract awarded by the U.S. Environmental Protection Agency (EPA) Region 5 to EA Engineering, Science, and Technology, Inc., PBC, a for-profit environmental consulting and engineering firm. The $9,994,121.71 Firm Fixed Price contract is for GLLA (Great Lakes Legacy Act) funding for Spirit Lake Phase 2 dredging in the RAC 3 (Remedial Action Contract 3) region. The contract has an ultimate completion date of March 25, 2025 and does not have a set-aside designation. EA...
This is a federal contract award from the Environmental Protection Agency (EPA) Region 5 to EA Engineering, Science, and Technology, Inc., PBC, a for-profit environmental consulting and engineering firm, to perform remedial action under the Great Lakes Legacy Act (GLLA) for the Spirit Lake project in Minneapolis, Minnesota. The contract has a ceiling value of $19,651,517.07 and a period of performance through March 28, 2025. The contract is a firm fixed price delivery order, with no set-aside...
The Environmental Protection Agency Region 5 awarded a $214,121 firm fixed price delivery order to EA Engineering, Science, and Technology, Inc. to provide post-remedial design support for the Great Lakes Legacy Act Spirit Lake former Duluth Works site remediation in the St. Louis River Area of Concern. EA Engineering will support objectives outlined in the remedial design to address ongoing cleanup activities at the Superfund site in Chicago, Illinois under a schedule running from October...
EA Engineering, Science, and Technology, Inc., PBC (EA) has been awarded a $1.3 million firm fixed price delivery order against the U.S. Environmental Protection Agency (EPA) Region 5's GREAT LAKES ARCHITECT AND ENGINEERING SERVICES (GLAES) II indefinite delivery/indefinite quantity contract vehicle. EA will provide design revision services in support of EPA's Spirit Lake Estuary Site Phase 3 project located in Duluth, Minnesota. Work will be performed from October 2021 through September...
This is a firm fixed-price delivery order contract awarded by the U.S. Environmental Protection Agency (EPA) Region 5 to EA Engineering, Science, and Technology, Inc., PBC, a for-profit environmental consulting firm, for $556,025.10. The contract is for the assessment of contaminated sediments in the St. Louis River and Bay Area of Concern. EA Engineering was awarded this task order as part of the company's existing indefinite delivery contract with EPA Region 5 for Superfund and Great Lakes...
This is a delivery order contract awarded to EA Engineering, Science, and Technology, Inc., PBC, a for-profit environmental consulting and engineering firm, for the Great Lakes Architect and Engineering Services (GLAES) II Task Order to provide remedial action oversight services for the U.S. Environmental Protection Agency (EPA) Region 5 Spirit Lake Great Lakes Legacy Act (GLLA) project in Duluth, Minnesota. The contract has a ceiling value of $2,602,464.56 and a period of performance through...
This is a firm fixed-price delivery order contract awarded by the U.S. Environmental Protection Agency (EPA) Region 5 to EA Engineering, Science, and Technology, Inc., PBC, a for-profit environmental consulting and engineering firm. The contract, valued at $5,099,386.53, is for Superfund and Great Lakes Architect & Engineering Services (SFGLAES) related to a Torch Lake drum removal pilot study. The contract is not set aside for any specific business type. EA Engineering has extensive...
  • EPR51110
    Indefinite Delivery Contract
  • EPR51110-0031
    Delivery Order

This federal contract award, with an ID of EPR51110/0031, was issued by the U.S. Environmental Protection Agency (EPA) Region 5 to EA Engineering, Science, and Technology, Inc., PBC, a for-profit environmental consulting firm. The $2,604,189.16 firm-fixed-price contract is for the Preliminary Design Investigation (PDI) activities at the Spirit Lake site in the St. Louis Area of Concern (AOC) to collect additional data necessary to refine the extent of contamination and facilitate the Remedial Design (RD).

The contract includes several subcontract awards to support various aspects of the PDI, such as sonic drilling, porewater organics analysis, field support, and cultural resources evaluation. Subcontractors include Cascade Drilling, L.P., University of North Dakota, Barr Engineering CO., Cascade Remediation Services LLC, Veit & Co Inc., Materials Testing Consultants Inc., Braun Intertec Corp, Testamerica Laboratories, Inc. (Eurofins Testamerica), and R. Christopher Goodwin & Associates, Inc. The contract does not utilize any set-aside designations.

This contract supports the EPA's Superfund program, which aims to clean up hazardous waste sites across the United States. The PDI activities at the Spirit Lake site are intended to provide the necessary data to develop effective remediation strategies for this contaminated area.

Generated 4/2/25, 4:55 PM