- The U.S. Army Corps of Engineers awarded a $2.1 million firm fixed-price definitive contract to Alberici Constructors Inc. for infrastructure improvements at Alton, Illinois. The project encompasses construction of a main lock and auxiliary lock, a dam featuring nine Tainter gates, and a fixed submersible dike extending to the Missouri side of the river. The contract carries an ultimate completion date of February 20, 2027, and represents open competitive contracting with no set-aside...
- This is a firm-fixed price definitive contract awarded by the U.S. Army Corps of Engineers' St. Louis District to Alberici Constructors Inc., a diversified construction company based in St. Louis, Missouri. The contract, valued at $1,369,732.18, is for the replacement and alteration of miter gate machinery at a navigation facility in East Alton, Illinois. This project supports the Army Corps of Engineers' civil works mission to maintain critical water infrastructure, such as locks and dams,...
- This firm-fixed price delivery order in the amount of $1,839,669.93 was awarded by the U.S. Army Corps of Engineers' St. Louis District to Alberici Constructors Inc. for work on the LD 25 Dam Gates and Service Bridge at the West Alton, Missouri facility. The contract does not have a set-aside designation. Alberici, a diversified construction company, has previously completed numerous civil works projects for the Army Corps of Engineers, including infrastructure maintenance and rehabilitation...
- This federal contract award to Alberici Constructors Inc. for the LOCK AND DAM NO. 25 DAM GATES project was issued by the Department of the Army Corps of Engineers. The $7,434,521.75 firm-fixed price delivery order contract does not have a set-aside designation. Alberici, a diversified construction company, provides infrastructure services to the Army Corps of Engineers, including work on locks, dams, and navigation structures. This award supports the Corps' civil works mission for maintenance...
- The U.S. Army Corps of Engineers awarded a $3.82 million firm fixed-price delivery order to Alberici Constructors Inc. for the replacement of cranes at Lock and Dam Nos. 24 and 25 located in West Alton, Missouri. The contract was awarded on August 20, 2019, with an ultimate completion date of October 30, 2022, and was not designated as a set-aside contract. This delivery order falls under Alberici's larger $35 million indefinite delivery contract with the Corps of Engineers specifically...
- This contract was awarded by the U.S. Army Corps of Engineers to Alberici Constructors Inc., a diversified construction company, to perform work on Lock and Dam No. 25 located in Winfield, Missouri. The $8,397,734.84 firm-fixed price delivery order contract involves the installation of dam gates and related rehabilitation services. Alberici has completed similar civil works projects for the Army Corps of Engineers at other lock and dam facilities along the Mississippi River, supporting the...
- This is a delivery order awarded by the U.S. Army Corps of Engineers, St. Louis District to Alberici Constructors Inc., a diversified construction company. The contract, valued at $1,852,020.93, is for LD25 and Service Bridge Task Order 0004, which involves work such as miter gate installation, machinery and electrical system overhaul, concrete demolition, and crane replacement at facilities along the Mississippi River. The contract is firm-fixed price and does not have a set-aside...
- This is a firm-fixed price delivery order awarded by the U.S. Army Corps of Engineers, St. Louis District, to Alberici Constructors Inc., a prime contractor, for SPAN 15 -LD 25 GATES & BRIDGE REPAIR at a facility in West Alton, Missouri. The contract has a completion date of November 12, 2017 and a ceiling value of $2,165,734.97. The award was made without a set-aside designation. Alberici Constructors is a diversified construction company that has previously performed infrastructure...
- This is a firm-fixed price delivery order awarded to Alberici Constructors Inc. by the U.S. Army Corps of Engineers' St. Louis District. The $3,772,552.78 contract is for LD25 and Service Bridge Paint and Repair at a location in West Alton, Missouri. This work is being performed under the larger $35 million and $7.6 million indefinite delivery contracts held by Alberici with the St. Louis District, which provide for rapid task order issuance to support the Corps' civil works mission of...
- This is a delivery order contract awarded by the U.S. Army Corps of Engineers to Alberici Constructors Inc., a prime contractor, for the LD25 and Service Bridge Dam Gates project. The firm-fixed-price contract, valued at $1,577,236.22, does not have a set-aside designation. Alberici is a diversified construction company that has previously completed various infrastructure projects for the Army Corps of Engineers, including work on locks, dams, and navigation structures. This delivery order...
The U.S. Army Corps of Engineers, St. Louis District has awarded Alberici Constructors Inc. a firm-fixed-price contract valued at $9,979,480.25 to perform alterations to the Melvin Price Main Lock Overlooks in Alton, Illinois. The work involves concrete demolition, removal and relocation of structural elements to shift the faces of two overlook buildings approximately 4.5 feet back from the lock wall, as originally solicited under Solicitation Number W912P921R0011. There is no set-aside designation. Alberici will utilize its experience completing civil works projects for the Corps, including navigation structure rehabilitation and facility alterations. This award draws upon Alberici's capabilities under its indefinite delivery contracts with the St. Louis District for services such as pier rehabilitation and crane replacement valued at $35 million and $7.6 million, respectively.
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
MPLD MAIN LOCK OVERLOOK ALTERATIONS | W912P921R0011 | Department of the Army Corps of Engineers Engineering District St Louis | Pre-Solicitation 1/1 | 5/13/21, 12:10 PM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| A00004 | Change Order | $6.5k | 7/21/23 | |
| A00003 | Change Order | $40.0k | 6/28/23 | |
| A00002 | Change Order | $7.0k | 4/13/23 | |
| A00001 | Change Order | $5.9k | 2/2/23 | |
| Not listed | Not listed | $9.9m | 9/24/21 |