This is a definitive contract awarded by the U.S. Army Corps of Engineers (USACE) Galveston District to Callan Marine LIMITED, a Texas-based dredging company, for maintenance dredging services along a 15-mile stretch of the Gulf Intracoastal Waterway (GIWW) between High Island and the Causeway in Galveston and Chambers Counties, Texas. The firm-fixed price contract, valued at $7,122,601.25, requires Callan Marine to dredge approximately 1.5 million cubic yards of material to restore navigability...
The U.S. Army Corps of Engineers awarded a $11,497,965.25 firm-fixed price contract to Orion Marine Construction, Inc. (doing business as Misener Marine Construction) for pipeline dredging services along the Gulf Intracoastal Waterway between Corpus Christi Bay and Port Isabel, Texas. The contract requires dredging approximately 1,400,000 cubic yards between November 1 and February 28, with options to dredge an additional 376,000 cubic yards. This unrestricted contract was awarded under the...
This is a $6,074,302.24 definitive, firm-fixed price contract awarded by the U.S. Army Corps of Engineers to Callan Marine LTD, a Texas-based dredging company, for pipeline shallow draft dredging along the Gulf Intracoastal Waterway, San Bernard River Channel, and Colorado River Channel in Texas. The contract includes the base effort of dredging approximately 1.1 million cubic yards of material from the Gulf Intracoastal Waterway, as well as three optional efforts totaling an additional...
The U.S. Army Corps of Engineers, Galveston District awarded a $7.7 million firm fixed-price contract to Mike Hooks, LLC for pipeline dredging services along the Gulf Intracoastal Waterway between Matagorda Bay and Corpus Christi Bay in Texas. The scope of work involves maintenance dredging of approximately 1.5 million cubic yards of material between station 1085+000 and station 1138+000, with dredged material to be placed in designated open water areas and beneficial use sites. The solicitation...
The U.S. Army Corps of Engineers awarded a $9.94 million firm-fixed-price construction contract to Inland Dredging Company, LLC for pipeline dredging along the Gulf Intracoastal Waterway from Freeport Harbor to Upper Matagorda Bay in Brazoria and Matagorda Counties, Texas. The original solicitation sought offers to dredge approximately 1 million cubic yards of material from Sections 1 through 15 of the waterway, with options to dredge additional sections totaling over 1.9 million cubic yards. No...
The U.S. Army Corps of Engineers awarded a $11,230,523.25 firm-fixed price contract to Inland Dredging Company, L.L.C. for maintenance dredging of the Gulf Intracoastal Waterway (GIWW) between Corpus Christi Bay and Port Isabel, Texas, including optional sections. The contract has a completion date of May 5, 2024 and was awarded on September 12, 2023 with no set-aside designation. This contract is part of the Army Corps of Engineers' civil works program to maintain navigable waterways for...
The U.S. Army Corps of Engineers, Galveston District awarded Orion Marine Construction, Inc., doing business as Misener Marine Construction, a $18.6 million firm-fixed-price contract to provide pipeline dredging services for Galveston Harbor and Channel in Galveston County, Texas. Under the terms of the contract, the contractor will dredge approximately 3.2 million cubic yards of material from the harbor and channel using submerged pipeline. The contractor has the option to dredge an...
The U.S. Army Corps of Engineers awarded a $10,749,115.42 definitive, firm-fixed price contract to Inland Dredging Company, L.L.C. for maintenance dredging of the Gulf Intracoastal Waterway from Freeport to Upper Matagorda Bay in Texas. The contract, which was not set aside, involves dredging approximately 1.3 million cubic yards between mile markers 596 to 902 and placing the material in upland confined, open water and surf zone areas. The contract also includes an option to dredge an...
The U.S. Army Corps of Engineers awarded a $104,974,200 firm-fixed-price definitive contract to Callan Marine, LTD., a Texas-based dredging company, for the Brazos Island Harbor Channel Deepening Phase II project in Cameron County, Texas. The contract requires dredging approximately 7,012,000 cubic yards of material from the main channel and turning basin using pipeline dredging, with all material to be placed in Placement Area 5B. The work is to be completed within an estimated 610 calendar...
The U.S. Army Corps of Engineers awarded a $3,000 firm fixed price delivery order against the Galveston District Rapid Response Pipeline Dredging master indefinite-delivery/indefinite-quantity contract to Callan Marine LTD for minimum guarantee services to address unanticipated shoaling along the Texas coast. Callan Marine, LTD will perform the work as the prime contractor under the five-year ordering period of performance set to run from April 2020 through April 2025. The delivery order was...