The U.S. Army Corps of Engineers, Mobile District, awarded a $72,657,737.00 firm-fixed-price contract to The Dutra Group, doing business as Dutra Dredging, for the Mobile Harbor Deepening & Widening Phase 6 project. This project involves dredging and widening portions of the Upper Bay Channel and Turning Basin in Mobile, Alabama between stations 226+16 to 337+00. The contract is not set-aside.
The Dutra Group is an experienced federal contractor, holding several Indefinite Delivery Contracts (IDCs) with the U.S. Army Corps of Engineers and the Department of the Navy for dredging and waterfront construction services. This particular project is part of the ongoing efforts by the U.S. Army Corps of Engineers to maintain critical maritime infrastructure and navigable depths in the Mobile Harbor. The contract has a performance period through March 13, 2025.