- This is a $16,128,537.95 firm-fixed price contract awarded by the U.S. Army Corps of Engineers to Abhe & Svoboda, Inc., a small business construction services provider, for the repair of six tainter gates at Kerr Lake in Oklahoma. The contract is for 730 calendar days with a completion date of November 25, 2023. The original solicitation was a sources sought notice to gain knowledge of industry capabilities, including small businesses, to perform the specialized repair and rehabilitation...
- This is a $4,841,172.80 definitive, firm-fixed price contract awarded by the U.S. Army Corps of Engineers to Abhe & Svoboda, Inc. for the repair of a bulkhead at the Point Pleasant Canal in New Jersey. The contract is not set aside and has a completion date of July 19, 2013. Abhe & Svoboda is a for-profit construction services company that specializes in corrosion control and protective coatings for critical infrastructure such as dams, waterways, and bridges. The company has over $47...
- The U.S. Army Corps of Engineers, St. Paul District awarded Abhe & Svoboda, Inc., a small business construction services provider headquartered in Jordan, Minnesota, a $19.3 million firm fixed-price definitive contract for routine gate maintenance at Lock and Dam 5A in Fountain City, Wisconsin. The contract work includes repainting and repairing dam roller gates, with potential scope expansion for sandblasting and painting bridge spans, gate component rehabilitation, and cathodic...
- <p>This is a $1,638,009.37 firm fixed-price contract awarded by the U.S. Army Corps of Engineers (USACE), Fort Worth District to B.W. Strayhorn Co, Inc., a self-certified small disadvantaged business. The contract is for fencing, gates, and fire lane clearing at Whitney Lake in Clifton, Texas. The work is being performed under the American Recovery and Reinvestment Act (ARRA) and has a completion date of February 16, 2011. The contract does not have a set-aside designation.</p>
- Abhe & Svoboda, Inc., a small business construction services provider headquartered in Jordan, Minnesota, was awarded a $15.9 million firm fixed-price definitive contract by the U.S. Army Corps of Engineers on August 30, 2023, for the Kaskaskia Tainter Gate Rehabilitation project at the Jerry F. Costello Lock and Dam in Modoc, Illinois. The contract involves comprehensive rehabilitation, surface preparation, blasting, and application of new paint systems to two tainter gates and a monorail...
- This is a $4,031,970 definitive contract awarded by the Bureau of Reclamation, a civilian agency within the U.S. Department of the Interior, to Abhe & Svoboda, Inc., a small business contractor. The purpose of the contract is to perform preventative maintenance on the dam gate at Friant Dam in Fresno, California, including removing and replacing existing coatings, seals, and the trash rack. This contract was set aside for small business concerns and has a completion date of March 16, 2025....
- Abhe & Svoboda, Inc., a Minnesota-based construction services firm specializing in protective coatings and infrastructure rehabilitation, was awarded a $34.6 million firm fixed-price definitive contract by the U.S. Army Corps of Engineers' Tulsa District on February 1, 2026, for the repair of Tainter Gates and associated components at the W.D. Mayo Dam in Spiro, Oklahoma. The contract is structured as a comprehensive turnkey project with an ultimate completion date of September 4, 2029,...
- This is a $310,513.06 Firm Fixed Price definitive contract awarded by the U.S. Army Corps of Engineers (USACE), Fort Worth District, to Interior-Exterior Construction Services, LLC, an 8(a) certified small disadvantaged business. The contract is part of a recovery project to ensure protection for the downstream public, requiring the contractor to provide all labor, supervision, tools, transportation, equipment, and materials necessary to paint a service bridge and repair gates at Bardwell Lake...
- <p>This is a $228,000.00 firm fixed price delivery order awarded by the U.S. Army Corps of Engineers to Affiliated Western, Inc. for the Whitney Powerhouse Elevator Rehab Project. The contract has a 90-calendar day period of performance from the notice to proceed, with a completion date of March 8, 2016. The work is located in Clifton, Texas. This award is not associated with a larger contract vehicle and does not have a set-aside designation.</p>
- The U.S. Army Corps of Engineers, Portland District awarded a $3,311,300.00 firm fixed price contract (W9127N22C0021) to Abhe & Svoboda, Inc., a small business, for the Hills Creek Reservoir Spillway Gate Replacement project. The contract involves structural demolition, fabrication, and installation of a new tainter gate, as well as electrical and mechanical system replacement. This contract award is associated with a pre-solicitation (Opportunity ID: 3d96df95b6d34eec90e8d14b02162957) that...
This is a $14,622,901.50 firm fixed-price definitive contract awarded by the U.S. Army Corps of Engineers Fort Worth District to Abhe & Svoboda, Inc., a for-profit construction services firm, for the repair and repainting of tainter gates at Whitney Lake in Clifton, Texas. The contract, which has no set-aside designation, was awarded on August 28, 2009 with a completion date of August 23, 2011. Abhe & Svoboda specializes in corrosion control and protective coatings for critical infrastructure managed by agencies like the Army Corps of Engineers and Bureau of Reclamation. This contract is part of the company's broader portfolio of over $47 million in prime contract awards since 2019 for rehabilitation services on dams, waterways, and other public works. The firm has also supported similar requirements as a subcontractor on contracts held by other prime partners.
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
RECOVERY--Y--PROJECT NUMBER 19920, Whitney Lake, TX | W9126G-09-B-0006 | Department of the Army Corps of Engineers Engineering District Fort Worth | Award Notice 2/2 | 8/7/10, 9:07 AM | |
RECOVERY--C--AMENDMENT TO ADD CORRECT BID OPENING DATE RECOVERY--STRUCTURAL REPAIR AND REPAINTING OF TAINTER GATE AT LAKE WHITNEY, CLIFTON, TEXAS | W9126G09B0006 | Department of the Army Corps of Engineers Engineering District Fort Worth | Award Notice 1/2 | 4/10/09, 1:56 PM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| P00006 | Other Administrative Action | ($123k) | 9/17/13 | |
| P00005 | Funding Only Action | ($628k) | 1/6/12 | |
| P00004 | Funding Only Action | ($110k) | 9/9/11 | |
| P00003 | Funding Only Action | $3.8m | 8/6/10 | |
| P00002 | Change Order | $304.0k | 6/16/10 |