Definitive Contract W9123616C0025

Award Date 9/19/16
Potential Completion Date 7/1/20
Potential Value $22M
Federal Agency
ENDIST Norfolk
Ultimate Awardee
Not listed
Federal Contract Vehicle
Set-Aside Type
No Set-Aside Used
Extent Competed
Full and Open Competition
Major Defense Program
Not listed
Pricing Type
Firm Fixed Price
Place of Performance
Langley AFB, VA 23665, USA
Solicitation Procedures
Negotiated Proposal / Quote
Number Of Offers Received
2
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed
Research Type
Not listed
Primary Consortia Member
Not listed
Similar Awards
The Department of the Navy Naval Facilities Engineering Command awarded a $7,951,714.00 firm-fixed price delivery order to W.F. Magann Corporation, a for-profit veteran-owned small business, to build floating piers supporting special boat teams at Fort Story, Virginia. The contract has a completion date of December 4, 2024 and was awarded on September 19, 2023. W.F. Magann Corporation has extensive experience providing heavy construction services to the U.S. Navy, including floating pier...
This is a $19,522,710.50 firm-fixed price definitive contract awarded by the Naval Facilities Engineering Command (NAVFAC), a Defense agency, to W.F. Magann Corporation, a veteran-owned small business. The contract is for bulkhead repairs at two locations, NSN CEP-175 and Z-308, in Fleet, Virginia. The work is a Total Small Business set-aside. W.F. Magann Corporation has a history of providing construction services to the U.S. Navy, including floating pier installation, dry dock and waterfront...
This $7,664,206.00 firm-fixed price delivery order contract was awarded by the U.S. Navy Installations Command (CNIC) to W.F. Magann Corporation, a veteran-owned small business, to replace the deperming station substation DS-20 at Naval Station Norfolk in Fleet, Virginia. The contract has a total small business set-aside and a completion date of December 17, 2025. Through this award, W.F. Magann Corporation will deliver construction services to replace critical electrical infrastructure...
This is a $312,408,308.64 definitive, firm fixed price contract awarded by the Naval Facilities Engineering Command (NAVFAC) to prime contractor Rq-Magann JV for the construction of a new 1,330-foot reinforced concrete pier and 800-foot wharf at Naval Station Norfolk in Norfolk, Virginia. The contract includes utilities infrastructure, a utility services building, security upgrades, and dredging. No set-aside designation was used for this full and open competition contract. Key subcontractors...
This is a $4,467,582.00 firm-fixed price delivery order awarded by the Department of the Navy Installations Command to W.F. Magann Corporation, a veteran-owned small business, for repairs to Pier A. The contract was set aside for small businesses. W.F. Magann Corporation is a provider of heavy construction services to the Department of the Navy, including work on floating piers, dry docks, and other waterfront infrastructure. This delivery order is part of the company's ongoing work supporting...
This is a firm-fixed price delivery order awarded by the Naval Facilities Engineering Command (NAVFAC), a Defense agency, to W.F. Magann Corporation, a veteran-owned small business. The $24,901,555.00 contract is for the installation of flood through valves on Caisson 8 at the Norfolk Naval Shipyard in Portsmouth, Virginia. The work is part of a larger Design-Bid-Build (DBB) project and is scheduled for completion by September 17, 2024. The contract does not have a set-aside designation. W.F....
This $7,311,989.13 firm-fixed-price definitive contract was awarded by the U.S. Department of Defense to Joint Forces Construction, L.L.C., a self-certified small disadvantaged, veteran-owned, and service-disabled veteran-owned business. The contract is for the construction of a Tactical Equipment Maintenance Facility (TEMF) Hardstand at Joint Base Langley-Eustis in Virginia. The contract does not have a set-aside designation. Joint Forces Construction, L.L.C. is a construction company that...
This is a firm-fixed-price delivery order contract awarded by the Defense Logistics Agency (DLA) Energy to Reliable Contracting Group, LLC, a small business headquartered in Louisville, Kentucky. The contract, valued at $8,367,337.05, is for facility repairs and maintenance of fuel storage tanks at Langley Air Force Base in Hampton, Virginia. The work includes SRM (Sustainment, Restoration, and Modernization) services for the facility's fuel infrastructure. This contract is not a set-aside and...
This is a firm-fixed price contract awarded by the Naval Facilities Engineering Command (NAVFAC) to W.F. Magann Corporation, a veteran-owned small business, to replace the caisson at Drydock No. 2 at the Naval Support Activity in Norfolk, Virginia. The contract has a ceiling value of $37,592,126.00 and the work is expected to be completed by September 7, 2023. The original solicitation, which did not have a set-aside designation, sought sources with experience in caisson construction, concrete...
This is a $1,624,446.68 firm fixed price delivery order awarded by the U.S. Army Corps of Engineers Omaha District to Burns & McDonnell Engineering Company, Inc. to provide architectural and engineering design, construction management, commissioning, and related services for a fuels project at Langley Air Force Base in Virginia. The contract was issued under the Army Architect-Engineer for Petroleum, Oils, and Lubricants 2012-2017 indefinite delivery vehicle. Key subcontractors include...

This is a $21,698,104.65 firm-fixed price contract awarded by the U.S. Army Corps of Engineers, Norfolk District to W.F. Magann Corporation, a veteran-owned small business, to replace the fuel pier and distribution facility at Joint Base Langley-Eustis in Virginia. The contract, which has a completion date of July 1, 2020, includes construction of a new concrete fuel pier, fender piles, mooring dolphins, a ground vehicle fueling facility with above ground storage tanks, and a utility building, as well as demolition of the existing fuel pier and dredging work for a turning basin. This effort was initially announced as a sources sought notice in November 2015, and the contract was subsequently awarded in September 2016 without the use of a small business set-aside.