Award Date 9/25/09
Potential Completion Date 7/31/10
Potential Value $193K
Ultimate Awardee
Not listed
Federal Contract Vehicle
Set-Aside Type
No Set-Aside Used
Extent Competed
Full and Open Competition
Major Defense Program
Not listed
Pricing Type
Firm Fixed Price
Place of Performance
Bloomington, MN 55425, USA
Solicitation Procedures
Sealed Bid
Number Of Offers Received
8
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed
Research Type
Not listed
Primary Consortia Member
Not listed
Similar Awards
This federal contract award, INF09PC75077, was issued by the U.S. Department of the Interior Fish and Wildlife Service (FWS) Region 3 to Olson Construction TRF Inc. for rehabilitation construction work on Ditch 11 South Dike Road at the Agassiz National Wildlife Refuge in Middle River, Minnesota. The contract is a definitive, firm-fixed-price contract with a ceiling value of $499,849.90 and was funded with $301,822.00 from the American Recovery and Reinvestment Act (ARRA). The contract does...
The Department of the Interior Fish and Wildlife Service Region 3 awarded a $126,225.00 firm fixed price purchase order contract to MN Boardwalks LLC, a self-certified small disadvantaged business, for the MN-MN VALLEY NWR-PIER & DOCK project. This contract was set aside for total small business participation and was awarded on September 2, 2020, with a completion date of January 29, 2021. The contract originated from a solicitation for the MN-MN VALLEY NWR-PIER & DOCK requirement that...
<p>The Department of the Interior Fish and Wildlife Service Region 3 awarded a firm fixed price purchase order contract in the amount of $157,300.00 to Sunram Construction, Inc., a self-certified small disadvantaged business, for the MN-MINNESOTA VALLEYNWR BASS PONDS BRIDGE project. This contract was set aside for small businesses. The original solicitation for this project was posted on June 25, 2020 and awarded on August 20, 2020.</p>
This federal contract award, INF13PC00072|INF16PD00805, was issued by the U.S. Department of the Interior's Fish and Wildlife Service to the prime contractor Short-Elliott-Hendrickson Inc. (SEH), a for-profit engineering and infrastructure services firm. The $842,369.43 firm-fixed-price delivery order contract is for bridge inspection and scour evaluation services across federal lands. SEH was not awarded this contract through a set-aside program. The contract is part of a larger $12 million...
The Department of the Interior Fish and Wildlife Service Region 2 awarded a $156,471.00 firm fixed price purchase order to Circle V Harvesting CO., a small business contractor, for the MN-MN Valley NWR-Road Trail Parking Repair project. This contract was set aside for small business concerns. The original solicitation did not use a set-aside. The contract will entail earthworks, road construction, and infrastructure repair services at the Minnesota Valley National Wildlife Refuge in Bloomington,...
This is a federal contract awarded by the Federal Highway Administration, a civilian agency, to Erickson Builders &amp; CO. Inc., a for-profit subchapter S corporation. The contract, valued at $595,621.03, is for the rehabilitation of approximately 0.22 miles of Winneshiek Road and three parking areas within the Upper Mississippi River National Wildlife and Fish Refuge. The work includes roadway reconditioning, asphalt pavement overlay, embankment stabilization, and other miscellaneous items....
This is a firm fixed-price delivery order contract awarded by the U.S. Department of the Interior (DOI) Fish and Wildlife Service Region 3 to RMD Holdings, LTD. (doing business as Nationwide Construction Group) for the Water Management Ditch Rehabilitation Project located at the Agassiz National Wildlife Refuge in Middle River, Minnesota. The contract, valued at $1,444,699.00, was awarded on May 28, 2010 with a performance period ending on November 30, 2011. The contract is for civilian agency...
The Department of the Interior Fish and Wildlife Service awarded a $3.9 million firm-fixed price construction contract to Loeffler Construction Consulting LLC for an addition and renovations project at the Minnesota Valley National Wildlife Refuge in Hennepin County, Minnesota. The contract is pursuant to Solicitation MN Valley ES Addition, which sought proposals for construction services including an approximately 1,600 square foot addition, remodeling of approximately 5,200 square feet of...
This federal contract award was issued by the U.S. Department of the Interior (DOI) Fish and Wildlife Service Region 3 to the prime contractor RMD Holdings, LTD. (doing business as Nationwide Construction Group) on May 27, 2010. The contract, which has a firm fixed price of $361,273.48 and an ultimate completion date of August 31, 2011, is a delivery order for the &quot;RECOVERY, TAS::14 1610::TAS, FFS PROJECT NO. R3LA, HEADQUARTERS BUILDING ENERGY RETROFIT, SHERBURNE NWR&quot; project. This...
This is a firm fixed-price purchase order awarded by the U.S. Department of the Interior (DOI) Fish and Wildlife Service (FWS) Region 3 to Erickson Builders &amp; Co. Inc., an emerging small business. The contract is for the installation of snow guards and a gutter on the maintenance building at the Sherburne National Wildlife Refuge located in Zimmerman, Minnesota. The contract has a ceiling value of $24,951.05 and a completion date of August 19, 2010. The purchase order is set aside for an...

This federal contract award, INF30181RC130, was issued by the U.S. Department of the Interior (DOI) Fish and Wildlife Service Region 3 to Erickson Builders & CO. Inc. The contract is for the construction of a pre-engineered bridge, approximately 90 feet in length, at the Minnesota Valley National Wildlife Refuge (NWR) in Shakopee, Minnesota. The work includes removing existing timber abutments and steel sheet pile, excavation, constructing concrete abutments, installing a steel and timber pre-engineered bridge, and adding gravel approach paths and rip rap protection. This is a firm fixed-price contract with a ceiling value of $192,635.60. The contract does not have a set-aside designation and the ultimate completion date is July 31, 2010.