Definitive Contract INF15PC00210
Award Date 9/18/15
Potential Completion Date 7/30/16
Potential Value $192K
Federal Agency
Ultimate Awardee
Not listed Federal Contract Vehicle
- Not listed
Set-Aside Type
8(a) Sole Source
Extent Competed
Not Available for Competition
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Los Banos, CA, USA
Solicitation Procedures
Only One Source
Number Of Offers Received
1
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- <p>This is a $3,932,139.36 firm fixed price definitive contract awarded by the U.S. Department of the Interior Fish and Wildlife Service to M.E. Avila Construction Corporation, a minority-owned, small disadvantaged business. The contract is for the first phase of construction of the EBF Administrative Facility, with a completion date of December 31, 2019. The contract was awarded on a sole-source basis under the 8(a) program for small disadvantaged businesses.</p>
- This is a federal contract award from the U.S. Department of the Interior (DOI) Fish and Wildlife Service Region 1 to M.E. Avila Construction Corporation, a minority-owned small disadvantaged business, for the rehabilitation of a shop at the Kern National Wildlife Refuge in Delano, California. The contract has a ceiling value of $328,606.00 and is a definitive, firm-fixed price contract. The contract was awarded on August 12, 2016 with an ultimate completion date of April 30, 2017. The...
- <p>This is a $1,170,980.00 firm-fixed-price definitive contract awarded by the U.S. Department of the Interior (DOI) Fish and Wildlife Service Region 4 to Mowa Barlovento LLC, JV, a minority-owned, self-certified small disadvantaged business. The contract is for the "PEE DEE NWR NEW VCS" project, which has a completion date of July 31, 2017. The contract was set aside for total small business participation.</p>
- This is a Definitive Contract awarded by the U.S. Department of the Interior (DOI) Fish and Wildlife Service Region 2 to De LOS Santos Construction, Inc., a Minority Owned, Self Certified Small Disadvantaged Business, for the Rehabilitation of Facilities. The contract has a Firm Fixed Price of $544,264.71 and an Ultimate Completion Date of June 30, 2010. The contract was awarded on October 13, 2009 and does not have a Set-Aside designation. As a Civilian agency, the DOI Fish and Wildlife Service...
- This is a firm fixed-price purchase order contract awarded by the U.S. Department of the Interior (DOI) Fish and Wildlife Service Region 2 to DBA Construction Inc., a self-certified small disadvantaged business, for the TAS::14 1610::TAS ALCHESAY/WILLIAMS CREEK NFH RACEWAYS project. The contract has a ceiling value of $328,442.45 and a completion date of October 30, 2010. The contract does not have a set-aside designation. The contract was awarded on February 5, 2010 and is associated with the...
- This federal contract award is for the repair of basement water leaks at the Iroquois National Wildlife Refuge, awarded by the U.S. Department of the Interior Fish and Wildlife Service to M.E. Avila Construction Corporation. The contract was awarded on June 24, 2016 as a sole-source 8(a) set-aside, with a firm fixed price of $97,600.00 and a completion date of September 15, 2016. M.E. Avila Construction Corporation is a minority-owned, self-certified small disadvantaged business. The contract...
- <p>This is a $313,323.35 firm fixed price definitive contract awarded by the U.S. Department of the Interior Fish and Wildlife Service Region 1 to Contractor Services Group, Inc., an 8(a) certified small disadvantaged business. The contract is for the construction of an observation deck and vault toilet building in Willows, CA. The contract has an ultimate completion date of September 30, 2015. No additional context or information about larger vehicles or subcontractors is provided.</p>
- This is a $151,570.90 firm-fixed-price purchase order contract awarded by the U.S. Department of the Interior (DOI) Fish and Wildlife Service to S.T. Rhoades Construction Incorporated, a minority-owned small disadvantaged business, to rehabilitate the Eagle Wildlife Repository located in Denver, Colorado. The contract was awarded on a sole-source basis under the 8(a) program, which provides contracting opportunities to small businesses owned by socially and economically disadvantaged...
- This is a $3,188,000.00 firm fixed price delivery order contract awarded to Marrero, Couvillon & Associates, L.L.C., a minority-owned small disadvantaged business, to replace a damaged hurricane bunkhouse. The contract is funded by the U.S. Department of the Interior (DOI) Fish and Wildlife Service Region 4 and has a completion date of May 31, 2026. The contract was not set aside for any particular business category. Marrero, Couvillon & Associates holds several Indefinite Delivery...
- <p>The Department of the Interior Fish and Wildlife Service awarded a $75,258.00 firm fixed price purchase order to 1776 Contractors Inc., a self-certified small disadvantaged business, for the completion of building renovations by January 31, 2025. This contract was set aside for small businesses.</p>
This is a $192,094.00 definitive, firm-fixed price contract awarded by the U.S. Department of the Interior (DOI) Fish and Wildlife Service Region 1 to M.E. Avila Construction Corporation, a minority-owned, self-certified small disadvantaged business and DOT-certified Disadvantaged Business Enterprise (DBE). The contract is for the rehabilitation of a shop facility, with a period of performance ending on July 30, 2016. The contract was awarded on September 18, 2015 as an 8(a) sole source set-aside.
Generated 4/1/25, 5:46 PM
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| 1 | Supplemental Agreement for work within scope | $0 | 6/28/16 | |
| Not listed | Not listed | $192.1k | 9/18/15 |