Definitive Contract AG4419C100274
Award Date 3/17/10
Potential Completion Date 9/20/11
Potential Value $349K
Funding Federal Agency
Contracting Federal Agency
Awardee
Ultimate Awardee
Not listed NAICS Category
PSC Category
Set-Aside Type
No Set-Aside Used
Federal Contract Vehicle
- Not listed
Extent Competed
Full and Open Competition
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Duluth, MN 55808, USA
Solicitation Procedures
Negotiated Proposal / Quote
Number Of Offers Received
5
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- <p>This is a $148,600 Firm Fixed Price purchase order awarded by the U.S. Department of Agriculture Forest Service to Bowman Construction Co Inc., a self-certified small disadvantaged business, for an aggregate crushing project. The contract has a total small business set-aside designation and is to provide gravel crushing services for the Superior National Forest in northeastern Minnesota. The contract was awarded on September 12, 2017 with a completion date of June 30, 2018.</p>
- This is a firm fixed-price definitive contract awarded by the U.S. Forest Service (USFS), Region 1 - Northern Region, to R & R Conner, Inc., a small business, for $154,056.97. The contract, which is funded under the American Recovery and Reinvestment Act (ARRA) and falls under the ARRA-FS CAPITAL IMPROVEMENT AND MAINTENANCE program, is for gravel crushing and stockpiling at the Tough Creek Pit in the Bitterroot National Forest. The contract has an ultimate completion date of November 15,...
- This is a $3,220,242.55 definitive firm fixed-price contract awarded by the U.S. Department of Agriculture's Forest Service, Region 1 - Northern Region, to Wood's Crushing And Hauling, Inc., a small business based in Idaho. The contract is for the RECOVERY WESTSIDE ROAD #895 RECONSTRUCTION/REPAVING PROJECT CIM-0110-02R-10 under the agency's ARRA-FS CAPITAL IMPROVEMENT AND MAINTENANCE major program. The work involves road grading, surfacing, and maintenance services in national forests across...
- <p>This is a $398,050.00 firm-fixed-price purchase order contract awarded by the U.S. Forest Service, Rocky Mountain Region (Region 2) to Rogers Construction, Inc., a small business subchapter S corporation, for rock crushing services at Custer Peak. The contract was set aside for total small business participation and has a completion date of June 30, 2018. This contract is not associated with a larger vehicle.</p>
- This is a $227,976.00 definitive contract awarded by the U.S. Department of Agriculture's Forest Service to Wood's Crushing And Hauling, Inc., a small business based in Idaho. The contract is for road maintenance, construction, and repair services in the Kootenai National Forest, including foothill aggregate placement and work on the Fortine Road. This contract is part of the Forest Service's ARRA-FS CAPITAL IMPROVEMENT AND MAINTENANCE program, which is funded through the American Recovery and...
- This is a definitive, firm fixed-price contract awarded by the U.S. Department of Agriculture's Forest Service to Wood's Crushing And Hauling, Inc., a small business based in Idaho. The $624,530.35 contract is for gravel crushing and placement services in support of the Restored Ecosystems and Fire Suppression activity under the American Recovery and Reinvestment Act (ARRA). The work is being performed in Thompson Falls, Montana. Wood's Crushing And Hauling has been a long-standing Forest...
- This is a firm fixed-price definitive contract awarded by the U.S. Department of Agriculture's Forest Service to Wood's Crushing And Hauling, Inc., a small business based in Sandpoint, Idaho. The $116,978.61 contract is for capital improvement and maintenance recovery work, primarily consisting of road grading, surfacing, and maintenance services in national forests across Idaho. This work supports the Forest Service's natural resource management and public land access initiatives in the region....
- <p>This is a firm fixed-price purchase order contract awarded by the Operations Center Southwest, a civilian agency, to Coal Bed Creek Construction Inc., a small business contractor, for the Timberland Mastication Project. The contract has a ceiling value of $82,150.00 and an ultimate completion date of November 8, 2010. The contract is set aside for total small business participation. No additional context or subcontractor information is provided.</p>
- This is a $340,000.00 firm-fixed-price definitive contract awarded by the United States Department of Agriculture (USDA) Forest Service, Southwestern Region, to Schuck Development Corp, a for-profit small business, to provide quarrying, aggregate production, crushing, and stockpiling services. The contract, which has a period of performance ending on November 30, 2015, is for the "DILLMAN PIT CRUSH & STOCKPILE 2015" project, which involves clearing, grubbing, stripping topsoil,...
- This is a $447,318.70 firm fixed-price definitive contract awarded by the U.S. Department of Agriculture Forest Service to Price Contracting Inc., a veteran-owned small business contractor. The contract is for the South Zone Bridge Restoration Project - Cliff Creek Bridge Construction Contract, which involves road, bridge, and infrastructure work supporting Forest Service operations in the Northern Region. The contract is not a set-aside. Price Contracting holds multiple active Indefinite...
This is a $348,934.74 firm fixed-price definitive contract awarded by the Operations Center East, a civilian federal agency, to Bowman Construction Co Inc., a self-certified small disadvantaged business. The contract is for Forest Wide Maintenance Stockpile Crushing in the West Zone, which is part of the agency's Stockpile Crushing - West Zone major program. The contract was awarded on March 17, 2010 and has an ultimate completion date of September 20, 2011. The contract was not set aside.
Generated 4/2/25, 10:07 AM
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
RECOVERY: Forestwide Maintenance Stockpile Crushiing | AG-4419-S-10-0337 | Department of Agriculture Forest Service Washington Office Economic Recovery Operations Center East | Award Notice 1/1 | 1/12/10, 9:15 AM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| 5 | Close Out | ($6k) | 4/14/15 | |
| 4 | Close Out | $0 | 9/20/11 | |
| 3 | Supplemental Agreement for work within scope | $188.5k | 7/13/10 | |
| 2 | Supplemental Agreement for work within scope | $10.8k | 5/25/10 | |
| 1 | Other Administrative Action | $0 | 4/20/10 |