- This firm-fixed-price contract, awarded by NASA's Kennedy Space Center to JP Donovan Construction Inc., is for $14,329,167 to perform modifications to Mobile Launcher 1 and install an emergency egress system in support of the Artemis II mission. The work includes structural modifications, adding platforms and systems for emergency egress, installing ground cooling, upgrading facilities, and integrating electrical and monitoring systems. This contract is not set aside for any particular...
- NASA's Kennedy Space Center awarded a $10.9 million firm fixed-price delivery order to JP Donovan Construction Inc. for the fabrication of the Mobile Launcher 2 (ML-2) Exploration Upper Stage Umbilical (EUSU) and associated parts. The contract, awarded on September 13, 2019, with an ultimate completion date of August 31, 2025, was issued without a set-aside designation under the NASA Ground Support Equipment 2019 multiple award IDIQ contract. Work will be performed at the contractor's facility...
- JP Donovan Construction Inc., a small business general contractor based in Rockledge, Florida, was awarded a delivery order valued at $3.38 million on February 9, 2023, for Mission Launch 1 tubing removal and replacement work at Kennedy Space Center. The award is a firm fixed-price delivery order issued under NASA's Ground Support Equipment 2019 multiple award indefinite delivery contract and does not utilize a set-aside designation. Work will be performed in Rockledge, Florida, with an ultimate...
- NASA's Kennedy Space Center awarded a $2.6 million firm fixed-price delivery order to JP Donovan Construction Inc. on September 8, 2023, for the fabrication of crew access arm (CAA) hinges and actuators for the Mobile Launcher 2 (ML2). The Mobile Launcher 2 is a critical ground support structure used at Kennedy Space Center for processing and launching NASA's Space Launch System (SLS) rockets. The delivery order, which extends through July 31, 2025, was issued under the NASA Ground Support...
- This is a firm fixed-price delivery order issued by NASA's Kennedy Space Center to JP Donovan Construction Inc., a small business contractor, under the NASA Ground Support Equipment 2019 multiple award IDIQ contract. The $85,000 order is for the fabrication and delivery of a mobile launcher handling and access lifting sling, which is a critical piece of ground support equipment used to process and assemble flight hardware at the launch facility. JP Donovan Construction has a history of providing...
- This federal contract award, NNK16CA06C, was issued by NASA's Kennedy Space Center to JP Donovan Construction Inc., a small business general contracting firm based in Rockledge, Florida. The $2,626,614 firm-fixed-price contract is for reinforcing the catacomb roof at Launch Complex 39B to support the Space Launch System (SLS) 1B vehicle. The contract is not a set-aside and was awarded as a definitive contract on February 23, 2016, with a completion date of July 31, 2017. JP Donovan...
- NASA's Kennedy Space Center awarded a $9.72 million firm fixed-price delivery order to JP Donovan Construction Inc. for the fabrication and delivery of a crew access arm, with a completion date of January 30, 2026. The award was issued on December 7, 2023, without a set-aside designation and represents a task order under the NASA Ground Support Equipment 2019 multiple award indefinite delivery contract. JP Donovan Construction, a Rockledge, Florida-based general contractor with over fifteen...
- JP Donovan Construction Inc., a Rockledge, Florida-based small business contractor specializing in aerospace ground support equipment fabrication, was awarded a $8.57 million firm fixed-price delivery order on September 8, 2022, for the fabrication of the Core Stage Forward Skirt Umbilical, Core Stage Intertank Umbilical, and Core Stage Intratank Umbilical. These umbilicals are critical ground support systems used in the processing and launch operations of NASA's Space Launch System (SLS) Core...
- This firm-fixed-price delivery order was awarded by NASA's Kennedy Space Center to JP Donovan Construction Inc. under the NASA Ground Support Equipment 2019 multiple award IDIQ contract. The $848,191 contract is for the Vehicle Assembly Building (VAB) structural member reinforcement. The work will be performed in Rockledge, Florida. JP Donovan Construction is a general contracting firm based in Rockledge that specializes in fabricating and installing ground support equipment, test equipment, and...
- This is a federal contract award by the National Aeronautics and Space Administration (NASA) Kennedy Space Center to Met-Con, Inc. for the provision of mobile launcher handling and access platforms. The contract, which has a ceiling value of $1,200,795.44, is a delivery order placed against an Indefinite Delivery/Indefinite Quantity (IDIQ) contract vehicle. The contract is for firm fixed-price work and does not have a set-aside designation. Met-Con, Inc. is a construction company that has...
This firm fixed price contract, awarded by NASA's Kennedy Space Center to JP Donovan Construction Inc., a small business based in Rockledge, Florida, is for the installation of emergency egress system (EES) conveyance modifications on Mobile Launcher-1 (ML-1) and at Launch Complex 39B. The contract has a ceiling value of $17,344,596 and a period of performance through December 13, 2024. The contract was not set aside for any specific business category. The work involves structural modifications to ML-1 and the installation of a new EES conveyance system, including platforms, slide wires, basket assemblies, programmable logic control safety systems, and braking systems. This contract is likely part of NASA's broader efforts to upgrade ground support infrastructure and processing capabilities at the Kennedy Space Center to support future spaceflight missions.
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
Emergency Egress System (EES) Conveyance | 80KSC021ZCS006L | National Aeronautics and Space Administration Kennedy Space Center | Pre-Solicitation 1/3 | 4/22/21, 2:05 PM | |
Mobile Launcher 1 (ML-1) Emergency Egress System (EES) Conveyance | 80KSC021R0029 | National Aeronautics and Space Administration Kennedy Space Center | Pre-Solicitation 2/3 | 5/16/21, 2:01 PM | |
Mobile Launcher 1 (ML-1) Emergency Egress System (EES) Conveyance | 80KSC021R0029 | National Aeronautics and Space Administration Kennedy Space Center | Solicitation 3/3 | 6/30/21, 4:07 PM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| P00051 | Supplemental Agreement for work within scope | ($60k) | 9/23/25 | |
| P00050 | Supplemental Agreement for work within scope | $1.5k | 2/13/25 | |
| P00049 | Supplemental Agreement for work within scope | $28.1k | 1/29/25 | |
| P00048 | Other Administrative Action | $0 | 12/20/24 | |
| P00047 | Supplemental Agreement for work within scope | $155.9k | 9/27/24 |