Definitive Contract 69056726C000002
- Not listed
- This is a firm-fixed-price construction contract awarded by the Federal Highway Administration, a civilian agency, to KH Civil Contractors, Inc. for the MT DAR MALM 2025(1), Defense Access Roads FY 2025 project. The contract, which has a ceiling value of $7,137,926.45, is for the resurfacing and improvement of existing Minuteman Missile Base Roads in Fergus County, Montana. The work includes the application of 4 inches of new aggregate and calcium chloride, as well as subexcavation and...
- The Federal Highway Administration awarded a $6.73 million firm fixed-price definitive contract to Century Companies, Inc. (doing business as Century Paving) on January 3, 2025, for construction services on the MT Flap Valley 20(1) Duck Creek Road project near Glasgow, Montana. The project encompasses roadway reconditioning, aggregate surfacing and stabilization, asphalt surfacing, subexcavation, and drainage improvements across 4.85 miles of gravel road, with work to include the addition of...
- The Federal Highway Administration awarded a $4.58 million delivery order to M.a. Deatley Construction, Inc. for the MT Flap Park 2021(1) project in Gardiner, Montana. The work encompasses improvements and preservation of the Old Yellowstone Trail South, including drainage installation, roadway reconditioning, aggregate surfacing, signage, and the addition of 200 flexible delineators. This delivery order was issued without a set-aside designation and carries an ultimate completion date of...
- The Department of Transportation Federal Highway Administration awarded a $3.3 million firm fixed price delivery order contract to Century Companies, Inc., doing business as Century Paving, to complete work on MT MUSSELSHELL 192(1). As the prime contractor, Century Paving will be responsible for road construction services on the identified project in Billings, Montana, running from May 22, 2020 through November 3, 2020. No set aside designation or subcontractors were indicated. The Federal...
- This is a definitive contract awarded by the Department of Transportation Federal Highway Administration to N.A. Degerstrom, Inc., a for-profit, woman-owned, and Subchapter S Corporation, for the MT FLATHEAD 917(2), BLACKTAIL ROAD SURFACE IMPROVEMENT PHASE 2 project. The contract has a firm fixed price of $3,045,455.19 and a completion date of October 16, 2018. The project does not have a set-aside designation. Major subcontractors include L.H.C., Incorporated, a veteran-owned business, for...
- This is a $8,237,263.44 firm fixed price definitive contract awarded by the Federal Highway Administration, a civilian agency, to Shumaker Trucking & Excavating Contractors, Inc., a small business. The contract is for the MT DAR MALM 2023(1) Defense Access Roads FY 2023 project, which consists of roadway reconditioning, aggregate surfacing, stabilization, and drainage improvements along approximately 5 miles of roadway south of Harlowton, Montana. This work was originally solicited as a...
- The Department of Transportation Federal Highway Administration awarded a $318,000 firm fixed price delivery order against its 2019 Architect Engineer Construction Management Inspection Support master IDIQ contract to Rocksol Consulting Group, Inc. The order is for rehabilitation services on Many Glacier Road and Glacier Route 14 in Montana, including road repairs and construction inspection. Work will be performed in Babb, Montana through January 2022. As part of its highway programs, the...
- The Department of Transportation Federal Highway Administration awarded a definitive contract valued at approximately $538,637.50 to Kovilic Construction Co Inc. The contract is associated with Solicitation Number 69056721B000024 issued by the DOT for repairs to highways and roads within the Helena-Lewis and Clark National Forest in Montana damaged by weather events in 2018. Work under the contract includes roadway excavation, placement of riprap, culvert installation, and turf establishment...
- This federal contract was awarded by the Federal Highway Administration (FHWA), a civilian agency under the U.S. Department of Transportation, to Riverside Contracting Inc. for the MT FLAP PARK 34(2), Shields River Road Surface Improvement project. The $9,647,397.13 firm-fixed-price contract involves up to 13.5 miles of paving, grading, and roadway reconditioning in Park County, Montana. The contract is not set aside for any specific business type. Riverside Contracting Inc. subcontracted...
- The U.S. Department of Transportation Federal Highway Administration awarded a $16,904,107.60 firm fixed price contract to Hamilton Construction Co., a for-profit construction company based in Springfield, Oregon, for the MT FLAP BOR 2980(1), Sun River Bridge Replacement project. The contract involves the construction of a new 3-span, 462-foot long precast-post-tensioned girder bridge with a precast concrete deck, approach embankments, and MSE walls in Augusta, Montana. This infrastructure...
The Federal Highway Administration awarded a $7.7 million firm fixed-price contract to KH Civil Contractors, Inc. on December 8, 2025, for construction services on the MT FLAP DOT 236(2) Winifred North project in Fergus County, Montana. This 18.60-mile road improvement initiative encompasses subexcavation, roadway reconditioning, aggregate surfacing and stabilization, guardrail installation, cattle guard placement, and signage implementation. The project extends from near a Defense Access Road facility northwest to a Missouri River bridge crossing and includes placement of multiple culvert pipes, guardrail terminal sections, and two cattle guards. The work is scheduled for completion by October 30, 2026, and was awarded through full and open competition without set-aside designation. The procurement was conducted under the Highway, Street, and Bridge Construction classification (NAICS 237310) following a pre-solicitation notice posted in March 2024. The definitive contract utilizes firm fixed-price pricing, establishing clear cost accountability for the $7.7 million ceiling value. This award supports the Federal Highway Administration's infrastructure improvement mandate by enhancing rural transportation connectivity and safety in Montana, with particular attention to drainage management and accessibility upgrades along the specified corridor.
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
MT FLAP DOT 236(2), Winifred North | 69056724B000007 | Department of Transportation Federal Highway Administration | Pre-Solicitation 1/4 | 3/29/24, 3:52 PM | |
MT FLAP DOT 236(2), Winifred North | 69056726C000002 | Department of Transportation Federal Highway Administration | Award Notice 4/4 | 12/8/25, 4:23 PM | |
MT FLAP DOT 236(2), Winifred North | 69056724B000007 | Department of Transportation Federal Highway Administration | Solicitation 2/4 | 7/29/24, 3:04 PM | |
MT FLAP DOT 236(2), Winifred North | 69056725B000010 | Department of Transportation Federal Highway Administration | Solicitation 3/4 | 9/19/25, 10:37 AM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| Not listed | Not listed | $6.8m | 12/8/25 |