Definitive Contract 69056721C000021

Award Date 5/27/21
Potential Completion Date 11/19/21
Potential Value $3.6M
Ultimate Awardee
Not listed
Federal Contract Vehicle
Set-Aside Type
Total Small Business
Extent Competed
Full and Open Competition after exclusion of sources
Major Defense Program
Not listed
Pricing Type
Firm Fixed Price
Place of Performance
Burley, ID 83318, USA
Solicitation Procedures
Sealed Bid
Number Of Offers Received
8
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed
Research Type
Not listed
Primary Consortia Member
Not listed
Similar Awards
The Department of Transportation Federal Highway Administration awarded a $2.7 million firm fixed price contract to Crea Construction, Inc. to improve 7.6 miles of Warren Wagon Road between mileposts 7.6 and 9.6 in Idaho Valley, Idaho. The solicitation sought construction services including resurfacing, repairing road base, replacing guardrails, and installing new pavement markings. Key documents for the $6,459 project included plans, specifications, geotechnical reports and component...
The Department of Transportation Federal Highway Administration awarded a $4,091,831.63 firm fixed price contract to Hat Creek Construction & Materials, Inc., a for-profit small business, to rehabilitate Riverside Road and Lakeshore Drive in Nampa, Idaho. This contract, identified as ID CANYON 2013(1), has a completion date of October 25, 2017. As a small business set-aside, this contract supports the Federal Highway Administration's infrastructure improvement initiatives. Hat Creek...
The Department of Transportation Federal Highway Administration awarded a firm fixed price delivery order contract to Hat Creek Construction & Materials, Inc., a for-profit construction services company, for $1,819,365.69. The contract is for road rehabilitation work on two highways in Idaho, specifically ID ADAMS 63(5) COUNCIL/CUPRUM ROAD, MP 11.20 TO 28.62 and ID ADAMS 98(2) GOOSE LAKE ROAD, MP 0 TO 3.8. This contract does not have a set-aside designation. Hat Creek Construction &...
The Department of Transportation Federal Highway Administration awarded a $127,453 delivery order against its 2019 Architect Engineer Construction Management Inspection Support master IDIQ to Nwi&T Atkins SB JV, LLC. The firm fixed price order is for ID CASSIA 972(1) WEST MILNER ROAD CI SERVICES in Burley, Idaho, and runs from June 30, 2021 through December 30, 2021. The 2019 master IDIQ, valued at an estimated $500 million over 5 years, supports the DOT's infrastructure programs through...
This firm-fixed-price contract, awarded by the Federal Highway Administration (FHWA) to Construction Solutions Group, LLC, a small business contractor, is for the construction project to widen shoulders and install a box culvert along 4.05 miles of roadway in Caldwell, Idaho. The total contract value is $5,010,985.20, and the ultimate completion date is August 29, 2025. The original solicitation was a pre-solicitation notice seeking qualified contractors for this $5-7 million project, which...
Valley Fence Incorporated received a definitive contract valued at $4,655,616.80 from the Department of Transportation Federal Highway Administration to resurface the last four miles of Camas Road within Glacier National Park, Montana. The firm fixed price contract calls for asphalt concrete paving, sub-excavation, slide repair, turnout rehabilitation, curb and gutter installation, sidewalk construction, underdrain installation, ditch reconditioning, and signing and striping along the...
This is a definitive firm-fixed-price contract awarded by the Federal Highway Administration (FHWA), a civilian agency, to Western Construction Inc., a for-profit Subchapter S corporation, for the reconstruction of Goose Lake Road in McCall, ID. The contract has a ceiling value of $10,628,654.54 and a period of performance ending on September 29, 2017. The contract was awarded on March 2, 2016 and was not set aside for any specific business type. The contract is identified as ID PFH 98(1) and is...
The Department of Transportation's Federal Highway Administration (DOT FHWA) awarded a $9,835,671.16 firm fixed price definitive contract to M.a. Deatley Construction, Inc. (doing business as Ma Deatley Construction Inc.), a for-profit construction company, for the ID PFH 21(7), Warren Wagon Road project in McCall, Idaho. The contract was set aside for small businesses and had a completion date of November 1, 2019. As a prime contractor, M.a. Deatley Construction has previously received...
The U.S. Department of Transportation's Federal Highway Administration (FHWA) awarded a $12,904,423.07 firm fixed-price definitive contract to Kilgore Companies, LLC, doing business as Triple C Concrete, for road construction and improvement work in Moab, Utah. The contract, which was not set aside, covers a range of services including entrance road reconstruction, parking improvements, concrete work, safety enhancements, roundabout construction, road widening, cold in-place recycling,...
This $2,070,065.08 firm fixed price Delivery Order was awarded by the Department of Transportation Federal Highway Administration to Hat Creek Construction & Materials, Inc., a for-profit small business contractor. The contract funds surface preservation and pavement preservation work at Hells Gate State Park and on Dixie Road in Idaho. This Delivery Order is associated with a larger indefinite delivery/indefinite quantity vehicle, likely focused on infrastructure and transportation projects...

The Department of Transportation Federal Highway Administration awarded a $3.6 million firm fixed price definitive contract to Canyon Valley Concrete Inc. for construction improvements to West Milner Road in Burley, Idaho. The project involves widening approximately four miles of the existing two-lane road from 24 to 28 feet to accommodate increased commercial and recreational traffic, as described in Solicitation ID Cassia 972(1). The total small business set-aside contract is to perform clearing, grubbing, excavation, installation of aggregate base and asphalt pavement, and other construction activities necessary to meet the solicitation's specifications. Canyon Valley Concrete was the lowest of nine bids received by the February 11, 2021 deadline, which ranged from $3.6-$5.4 million. The engineer's estimate was $4.4 million. The work furthers the DOT's mission to improve transportation infrastructure through the Federal Highway Administration's Western Federal Lands Highway Division program.

Generated 12/29/23, 4:37 PM