- The U.S. Department of the Interior National Park Service Intermountain Region awarded a $993,671.00 firm fixed price delivery order contract to Weil Construction Inc., a minority-owned, self-certified small disadvantaged business, to rehabilitate the Kbar water system at Big Bend National Park in Texas. The contract was issued under the National Park Service Intermountain Region MATOC 2021-2026, a multiple award task order contract vehicle. The work includes replacing the existing 25,000-gallon...
- Edstrom Construction Inc. was awarded a $2.7 million firm fixed-price contract by the National Park Service to upgrade the wastewater treatment plant in Panther Junction, Big Bend National Park, Texas. The contract calls for replacing the existing 42,000 gallon per day plant with a new packaged treatment system. Work is to be completed within 325 calendar days. Funding is provided by the Department of the Interior National Park Service National Office. The acquisition was set aside for small...
- <p>This firm fixed-price purchase order contract was awarded by the National Park Service, Intermountain Region to Integritas Systems, L.L.C., a small business. The contract, valued at $87,100.00, is for the replacement of a duplex pressure booster pump set at Big Bend National Park in Texas. The work includes demolition and removal of the existing equipment as well as installation of new pumps, tanks, plumbing, wiring, and controls. The contract has a completion date of December 30, 2016.</p>
- This firm fixed-price delivery order contract, valued at $1,004,439.55, was awarded by the National Park Service Intermountain Region to Ridgway Valley Enterprises Inc., a small business commercial general contractor. The contract is for the replacement of the Rio Grande Village water tank and water line at Big Bend National Park in Texas. The work includes the installation of approximately 1,000 linear feet of 4-inch and 6-inch HDPE water lines, demolition of a 400,000-gallon steel water...
- All-Rite Construction, Inc. has been awarded a firm fixed price delivery order valued at two hundred forty-nine thousand two hundred nine dollars and one cent ($249,209.01) by the National Park Service Intermountain Region to replace approximately one thousand one hundred seventy-seven (1,177) linear feet of three-inch (3") high-density polyethylene (HDPE) waterline at Big Bend National Park in Texas. Work will include installation of a new water line at a minimum four-foot (4') bury...
- This is a $7,400.00 firm fixed price purchase order awarded by the Intermountain Region of the National Park Service, a civilian agency within the U.S. Department of the Interior. The contract is for cleaning and inspecting water tanks at Big Bend National Park in Texas, with a completion date of August 31, 2023. The contract was awarded to RON Perrin Water Technologies, Inc., a small business subchapter S corporation, under a total small business set aside. RON Perrin Water Technologies...
- <p>The Department of the Interior National Park Service Intermountain Region awarded a $488,094.25 firm fixed price delivery order contract to El Paso J.a.g., Inc. doing business as El Paso Jag Inc. to re-pipe and line the wastewater lift station at Big Bend National Park, Texas. The work is to be performed between July 26, 2022 and September 11, 2023 at the park located in Big Bend, Texas.</p>
- This is a federal contract award to All-Rite Construction, Inc., an SBA-certified HUBZone and small disadvantaged business based in Albuquerque, New Mexico. The contract, awarded by the National Park Service Intermountain Region, is for the rehabilitation of the Chisos Basin water system at Big Bend National Park in Texas. The contract has a ceiling value of $448,390.47 and is a firm fixed-price delivery order. The award date was August 20, 2015, and the ultimate completion date is December...
- This is a $2,556,852.58 definitive, firm-fixed price contract awarded by the Department of the Interior National Park Service to Guardian Construction, Inc., a minority-owned, 8(a) certified small disadvantaged business. The contract was awarded on a sole-source basis to perform bridge preservation work, including preventative maintenance, repair, and construction activities across seven bridge structures located in Big Bend National Park in Texas. The contract has a period of performance of 130...
- This is a $14,528,863.23 firm fixed price contract awarded by the National Park Service to Blue World Construction Inc., a small disadvantaged business, to rehabilitate the potable water distribution and wastewater collection systems at Fort Hancock in the Gateway National Recreation Area in New Jersey. The original solicitation sought design-build proposals to address deficiencies in the aging water infrastructure at this national park site. The 3-year contract, which has no set-aside...
This is a $17,880,692.00 firm fixed price definitive contract awarded by the National Park Service, a civilian agency under the Department of the Interior, to Blue World Construction Inc., a self-certified small disadvantaged business, to replace and upgrade the water infrastructure for two public water systems at Big Bend National Park in Texas. The contract has an ultimate completion date of August 13, 2026. The project scope includes rehabilitation of water treatment facilities and storage tanks, replacement of outdated distribution piping, and upgrades to accommodate increased demand and meet fire suppression requirements. The contract was awarded on an unrestricted full and open basis without any set-aside designation. There is no indication that this contract is associated with a larger contract vehicle.
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
BIBE 317515 Replace Park Water System | 140P2023R0048 | Department of the Interior National Park Service National Office | Award Notice 3/3 | 9/25/23, 4:21 PM | |
BIBE 317515 Replace Park Water System | 140P2023R0048 | Department of the Interior National Park Service National Office | Solicitation 2/3 | 3/28/23, 5:35 PM | |
Pre-Solicitation Notice | 140P2023R0048 | Department of the Interior National Park Service National Office | Pre-Solicitation 1/3 | 3/6/23, 4:02 PM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| P00003 | Supplemental Agreement for work within scope | $101.3k | 9/11/25 | |
| P00002 | Supplemental Agreement for work within scope | $1.3m | 6/18/25 | |
| P00001 | Supplemental Agreement for work within scope | $31.4k | 4/5/24 | |
| Not listed | Not listed | $16.5m | 9/25/23 |