Definitive Contract 12639220C0001

Award Date 5/19/20
Potential Completion Date 10/30/20
Potential Value $296K
Ultimate Awardee
Not listed
Federal Contract Vehicle
Set-Aside Type
Total Small Business
Extent Competed
Full and Open Competition after exclusion of sources
Major Defense Program
Not listed
Pricing Type
Firm Fixed Price
Place of Performance
Duluth, MN 55808, USA
Solicitation Procedures
Negotiated Proposal / Quote
Number Of Offers Received
4
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed
Research Type
Not listed
Primary Consortia Member
Not listed
Similar Awards
The U.S. Forest Service's Eastern Region (R9) has awarded a $418,953.20 firm-fixed-price delivery order contract to Gerit Hanson Contracting, Inc. for the replacement of a snowmobile trail bridge on the Chippewa National Forest. This award is part of a larger $7 million single-award indefinite delivery contract the firm holds for construction projects on the Chippewa National Forest through 2028. Gerit Hanson Contracting is a for-profit construction and road maintenance services provider based...
The U.S. Forest Service's Chippewa National Forest awarded a firm-fixed-price definitive contract worth $590,924.30 to Gerit Hanson Contracting, Inc. for road grading services. This total small business set-aside contract has a performance period from March 1, 2022 through February 28, 2027. Gerit Hanson Contracting is a for-profit construction and road maintenance service provider based in Illinois, with a long history of executing USDA Forest Service contracts in the Eastern Region. This award...
This is a firm fixed price definitive contract awarded by the USDA Forest Service's Eastern Region (R9) to S & R Reinforcing Inc., a self-certified small disadvantaged and woman-owned business. The $457,713.50 contract is for the replacement of a bridge on the Pigeon River, a project designated as a total small business set-aside. S & R Reinforcing has previously held Forest Service contracts, including a $181,057 bridge replacement task order and two $7 million Indefinite Delivery...
The USDA Forest Service awarded a $4,000 delivery order contract to Gerit Hanson Contracting, Inc. of Duluth, Minnesota for emergency mud lake box culvert repair work. The contract has a firm fixed price and period of performance from April 2020 through December 2023. Gerit Hanson Contracting will perform the required repair services for the USDA Forest Service's Eastern Region office in Duluth to address an immediate need. No subcontractors or set aside designations were identified. The...
This federal contract was awarded to High Country Conservation, LLC, a for-profit limited liability company, to perform repairs to a 246-foot suspension bridge in Manistee County, Minnesota. The work includes deck, railing, and curb replacement, cable adjustments, clamp replacement and painting, needle beam replacement, and stringer fascia board replacement. The contract has a ceiling value of $90,800.00 and was issued as a Blanket Purchase Agreement (BPA) call by the U.S. Forest Service's...
This is a $1,647,735.45 firm-fixed-price definitive contract awarded by the U.S. Department of Agriculture Forest Service to Larson Construction Co Inc., a woman-owned small business, to replace a five-span sawn timber bridge on the Chequamegon-Nicolet National Forest in Wisconsin with a new three-span bridge. The contract includes a steel H-pile with reinforced concrete abutments and piers, as well as a glulam timber superstructure, deck, and rails. The contract was set aside for small...
The Department of Agriculture Forest Service awarded a $35,640 firm fixed price delivery order contract to Gerit Hanson Contracting, Inc. of Duluth, MN for the Mabel Lake Rock Crossing project. Under this contract, Gerit Hanson Contracting will construct a rock crossing at Mabel Lake to improve access within the Eastern Region's forest lands. No subcontractors or set-aside designations were specified. The completion date for the project is November 30, 2020, supporting the Forest Service's...
The USDA Forest Service awarded a $106,950 firm fixed price delivery order to Gerit Hanson Contracting, Inc. of Cass Lake, Minnesota for road blading services in support of the agency's FY21 program on the Chippewa National Forest. Under the contract, Gerit Hanson will perform road maintenance activities including blading and grading to keep forest roads passable through November 30, 2021. No set-aside designation was applied to this award made using the Forest Service's Eastern Region...
This is a firm fixed price blanket purchase agreement (BPA) call awarded by the USDA Forest Service to S & R Reinforcing Inc., a woman-owned small business, to replace a deficient trail bridge in the Northeast Zone - Region 9 under the GAOA (Great American Outdoors Act) program. The contract has a ceiling value of $277,426.20 and a completion date of June 16, 2025. S & R Reinforcing Inc. has held previous Forest Service contracts, including a $181,057 bridge replacement project and two...
The Department of Agriculture Forest Service awarded a $1,204,445.60 firm fixed price definitive contract to A. Lindberg & Sons, Inc. to replace the Indian River Bridge on the Hiawatha National Forest in Manistique, Michigan. The contract is set aside for total small business participation. It will fulfill a solicitation seeking proposals to remove an existing deteriorated 66-foot long concrete bridge and replace it with a new 66-foot long by 18-foot wide timber bridge and abutments, along...

This definitive contract awarded by the USDA Forest Service Eastern Region to Gerit Hanson Contracting Inc. is valued at $295,653.72 to rehabilitate the Rice River Bridge located in the Chippewa National Forest in Minnesota. The solicitation sought a contractor to remove the existing asphalt and slotted drains, replace the deck railings, and improve the vertical alignment and drainage of the bridge. As a total small business set-aside awarded under the Forest Service's budget, Gerit Hanson Contracting will furnish all labor, materials, and equipment to complete the bridge rehabilitation in accordance with the provided scope of work, specifications and drawings over a five-month period ending in October 2020.